Landscape Evolution for the New Campus

01 Jun 17

Truly, the beauty of the new planting's growth  is the promise that it brings. Classrooms and buildings that are placed perfectly on the landscape only require nature to complete the ...

> Read more

New Campus Opening January 16, 2017

06 Feb 17

On January 16, 2017, Montessori School Bali welcomed its students onto their long anticipated new campus in the Berawa area of Canggu. The grass is down, vegetable plants are coming ...

> Read more

New Campus Update October 24, 2016

24 Oct 16

The aerial view of the campus on October 24, 2016 shows the landscaping near complete.  Preschool and Primary classrooms are complete and details are being reviewed.  The Administration and Infant ...

> Read more

New Campus Update: September 22, 2016

22 Sep 16

September 22, 2016: Acoustic ceiling and gable window with air vent in a Preschool classroom. Progress continues at a cracking pace on our new campus. Work on settling the landscape continues. ...

> Read more

New Campus Update: August 25, 2016

25 Aug 16

August 25, 2016: Joinery continues, with windows going into the classrooms. Progress steadily continues with our new campus, with joinery, windows, painting and work on the landscape all moving forward.  Delivery ...

> Read more

New Campus Update: July 29, 2016

29 Jul 16

July 29, 2016: Work progresses on the roadside gable end of the Preschool block. Work is progressing on the fascias, gable windows, and classroom and veranda ceilings.   July 29,2016: The acoustic ceiling ...

> Read more

New Campus Update: June 9, 2016

09 Jun 16

June 9, 2016: The Admin block is up and the roof is going on. The internal structure and joinery progresses in the Preschool and Primary classrooms as work continues on the ...

> Read more

New Campus Update: May 12, 2016

06 May 16

May 12: Preschool block Work on the steel structure for the Admin and Infant Community continues, while the roofs on the classrooms are now almost complete. May 12: Lower and Upper Primary ...

> Read more

Campus Update: April 15, 2016

15 Apr 16

It is exciting to see the classroom blocks for our new campus start to take shape as work accelerates on site. The steel structure is complete for the preschool and ...

> Read more

New Site Update: February 2016

16 Feb 16

The steel structure is being erected a block at a time, starting with the Preschool, which is already halfway there. Approximately 70% of the steel for all other classrooms, from ...